{"id":9467,"date":"2026-06-26T13:34:59","date_gmt":"2026-06-26T11:34:59","guid":{"rendered":"https:\/\/coneix.com\/cpm-camino-critico\/"},"modified":"2026-07-03T09:09:36","modified_gmt":"2026-07-03T07:09:36","slug":"cpm-cami-critic","status":"publish","type":"post","link":"https:\/\/coneix.com\/ca\/cpm-cami-critic\/","title":{"rendered":"CPM, la metodologia de planificaci\u00f3 de projectes del cam\u00ed cr\u00edtic"},"content":{"rendered":"\n<p class=\"wp-block-paragraph\">Hi ha projectes que comencen b\u00e9, amb un calendari ben definit i un equip coordinat, i que, malgrat aix\u00f2, acaben amb <strong>retards<\/strong> que ning\u00fa sap ben b\u00e9 d&#8217;on han sortit. En molts dels casos, el problema no \u00e9s la falta de planificaci\u00f3: \u00e9s que <strong>no s&#8217;han identificat les tasques que realment no podien esperar.<\/strong><\/p>\n\n\n\n<p class=\"wp-block-paragraph\">El <strong>m\u00e8tode del cam\u00ed cr\u00edtic (CPM, Critical Path Method) <\/strong>\u00e9s una eina de tota la vida que resol exactament aix\u00f2. En aquest article expliquem com funciona i per qu\u00e8 canvia la manera de gestionar un projecte.<\/p>\n\n\n\n<div id=\"ez-toc-container\" class=\"ez-toc-v2_0_85 counter-hierarchy ez-toc-counter ez-toc-custom ez-toc-container-direction\">\n<div class=\"ez-toc-title-container\">\n<p class=\"ez-toc-title\" style=\"cursor:inherit\">\ud83d\udcd1 Lo que encontrar\u00e1s en este art\u00edculo:<\/p>\n<span class=\"ez-toc-title-toggle\"><a href=\"#\" class=\"ez-toc-pull-right ez-toc-btn ez-toc-btn-xs ez-toc-btn-default ez-toc-toggle\" aria-label=\"Toggle Table of Content\"><span class=\"ez-toc-js-icon-con\"><span class=\"\"><span class=\"eztoc-hide\" style=\"display:none;\">Toggle<\/span><span class=\"ez-toc-icon-toggle-span\"><svg style=\"fill: #2dabe3;color:#2dabe3\" xmlns=\"http:\/\/www.w3.org\/2000\/svg\" class=\"list-377408\" width=\"20px\" height=\"20px\" viewBox=\"0 0 24 24\" fill=\"none\"><path d=\"M6 6H4v2h2V6zm14 0H8v2h12V6zM4 11h2v2H4v-2zm16 0H8v2h12v-2zM4 16h2v2H4v-2zm16 0H8v2h12v-2z\" fill=\"currentColor\"><\/path><\/svg><svg style=\"fill: #2dabe3;color:#2dabe3\" class=\"arrow-unsorted-368013\" xmlns=\"http:\/\/www.w3.org\/2000\/svg\" width=\"10px\" height=\"10px\" viewBox=\"0 0 24 24\" version=\"1.2\" baseProfile=\"tiny\"><path d=\"M18.2 9.3l-6.2-6.3-6.2 6.3c-.2.2-.3.4-.3.7s.1.5.3.7c.2.2.4.3.7.3h11c.3 0 .5-.1.7-.3.2-.2.3-.5.3-.7s-.1-.5-.3-.7zM5.8 14.7l6.2 6.3 6.2-6.3c.2-.2.3-.5.3-.7s-.1-.5-.3-.7c-.2-.2-.4-.3-.7-.3h-11c-.3 0-.5.1-.7.3-.2.2-.3.5-.3.7s.1.5.3.7z\"\/><\/svg><\/span><\/span><\/span><\/a><\/span><\/div>\n<nav><ul class='ez-toc-list ez-toc-list-level-1 ' ><li class='ez-toc-page-1 ez-toc-heading-level-2'><a class=\"ez-toc-link ez-toc-heading-1\" href=\"https:\/\/coneix.com\/ca\/cpm-cami-critic\/#Que_es_el_CPM_i_don_ve\" >Qu\u00e8 \u00e9s el CPM i d&#8217;on ve<\/a><\/li><li class='ez-toc-page-1 ez-toc-heading-level-2'><a class=\"ez-toc-link ez-toc-heading-2\" href=\"https:\/\/coneix.com\/ca\/cpm-cami-critic\/#Diferencia_entre_tasques_critiques_i_tasques_amb_marge\" >Difer\u00e8ncia entre tasques cr\u00edtiques i tasques amb marge<\/a><\/li><li class='ez-toc-page-1 ez-toc-heading-level-2'><a class=\"ez-toc-link ez-toc-heading-3\" href=\"https:\/\/coneix.com\/ca\/cpm-cami-critic\/#Com_identificar_el_cami_critic_en_un_projecte_exemple_pas_a_pas\" >Com identificar el cam\u00ed cr\u00edtic en un projecte: exemple pas a pas<\/a><\/li><li class='ez-toc-page-1 ez-toc-heading-level-2'><a class=\"ez-toc-link ez-toc-heading-4\" href=\"https:\/\/coneix.com\/ca\/cpm-cami-critic\/#Quan_combinar_el_CPM_amb_el_diagrama_de_Gantt\" >Quan combinar el CPM amb el diagrama de Gantt<\/a><\/li><\/ul><\/nav><\/div>\n<h2 class=\"wp-block-heading\"><span class=\"ez-toc-section\" id=\"Que_es_el_CPM_i_don_ve\"><\/span>Qu\u00e8 \u00e9s el CPM i d&#8217;on ve<span class=\"ez-toc-section-end\"><\/span><\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">El m\u00e8tode del cam\u00ed cr\u00edtic va n\u00e9ixer als anys cinquanta en el context de la ind\u00fastria aeron\u00e0utica i de la construcci\u00f3 nord-americana. L&#8217;objectiu era senzill: <strong>identificar, dins d&#8217;un conjunt de tasques interdependents, quina seq\u00fc\u00e8ncia determinava la durada total del projecte.<\/strong><\/p>\n\n\n\n<p class=\"wp-block-paragraph\">La idea de base \u00e9s que en tots els projectes hi ha tasques que depenen d&#8217;altres per poder comen\u00e7ar. <strong>Si una d&#8217;aquestes tasques s&#8217;endarrereix, tota la resta tamb\u00e9.<\/strong> El conjunt de tasques que formen aquesta cadena de depend\u00e8ncies sense cap marge de temps es coneix com a <strong>cam\u00ed cr\u00edtic<\/strong>.<\/p>\n\n\n\n<blockquote class=\"wp-block-quote is-layout-flow wp-block-quote-is-layout-flow\">\n<p class=\"wp-block-paragraph\">La durada del cam\u00ed cr\u00edtic \u00e9s la durada m\u00ednima possible del projecte.<\/p>\n<\/blockquote>\n\n\n\n<p class=\"wp-block-paragraph\">En els projectes d&#8217;arquitectura i enginyeria, on les fases es trepitgen, els agents externs (administracions, promotors, industrials) intervenen en moments concrets i els recursos es comparteixen entre enc\u00e0rrecs, tenir clara aquesta cadena \u00e9s un avantatge i una necessitat.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\"><span class=\"ez-toc-section\" id=\"Diferencia_entre_tasques_critiques_i_tasques_amb_marge\"><\/span>Difer\u00e8ncia entre tasques cr\u00edtiques i tasques amb marge<span class=\"ez-toc-section-end\"><\/span><\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">No totes les tasques d&#8217;un projecte tenen el mateix pes sobre el calendari final. Aquesta \u00e9s la distinci\u00f3 fonamental que el CPM aporta:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li><strong>Tasques cr\u00edtiques:<\/strong> qualsevol retard en aquestes tasques implica un retard equivalent en la data de lliurament del projecte. No hi ha marge. Un dia perdut \u00e9s un dia perdut per a tothom.<br><\/li>\n\n\n\n<li><strong>Tasques amb marge (float):<\/strong> s\u00f3n tasques que es poden iniciar m\u00e9s tard, o allargar lleugerament, sense afectar la data final. Tenir clar quin \u00e9s el seu marge permet prioritzar recursos en els moments adequats.<\/li>\n<\/ul>\n\n\n\n<p class=\"wp-block-paragraph\">El marge d&#8217;una tasca es calcula com la difer\u00e8ncia entre la data l\u00edmit en qu\u00e8 pot acabar sense afectar el projecte i la data en qu\u00e8, seguint el ritme normal, s&#8217;acabaria. Una tasca amb marge zero \u00e9s, per definici\u00f3, una tasca cr\u00edtica.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Saber on tens marge i on no \u00e9s el que permet prendre decisions sobre on posar l&#8217;atenci\u00f3, on pots redistribuir hores d&#8217;equip i on, en canvi, no pots permetre cap desviaci\u00f3.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\"><span class=\"ez-toc-section\" id=\"Com_identificar_el_cami_critic_en_un_projecte_exemple_pas_a_pas\"><\/span>Com identificar el cam\u00ed cr\u00edtic en un projecte: exemple pas a pas<span class=\"ez-toc-section-end\"><\/span><\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">Imagina un projecte d&#8217;habitatge unifamiliar amb les fases habituals. Simplificant, les tasques principals i les seves depend\u00e8ncies podrien ser les seg\u00fcents:<\/p>\n\n\n\n<figure class=\"wp-block-table\"><table><thead><tr><th>Tasca<\/th><th>Durada estimada<\/th><th>Dep\u00e8n de<\/th><\/tr><\/thead><tbody><tr><td><strong>A.<\/strong> Sol\u00b7licitud de llic\u00e8ncia<\/td><td>60 dies<\/td><td>\u2014<\/td><\/tr><tr><td><strong>B.<\/strong> Redacci\u00f3 del projecte executiu<\/td><td>45 dies<\/td><td>\u2014<\/td><\/tr><tr><td><strong>C.<\/strong> Concessi\u00f3 de llic\u00e8ncia<\/td><td>30 dies<\/td><td>A<\/td><\/tr><tr><td><strong>D.<\/strong> Licitaci\u00f3 industrial<\/td><td>20 dies<\/td><td>B, C<\/td><\/tr><tr><td><strong>E.<\/strong> Inici d&#8217;obra<\/td><td>5 dies<\/td><td>D<\/td><\/tr><tr><td><strong>F.<\/strong> Execuci\u00f3 d&#8217;estructura<\/td><td>40 dies<\/td><td>E<\/td><\/tr><tr><td><strong>G.<\/strong> Tancaments i instal\u00b7lacions<\/td><td>60 dies<\/td><td>F<\/td><\/tr><tr><td><strong>H.<\/strong> Lliurament i certificat final<\/td><td>15 dies<\/td><td>G<\/td><\/tr><\/tbody><\/table><\/figure>\n\n\n\n<p class=\"wp-block-paragraph\">Si seguim les depend\u00e8ncies, el cam\u00ed A \u2192 C \u2192 D \u2192 E \u2192 F \u2192 G \u2192 H suma <strong>230 dies.<\/strong> El cam\u00ed alternatiu que inclou B es resol en menys temps perqu\u00e8 la redacci\u00f3 del projecte executiu (45 dies) acaba molt abans que la concessi\u00f3 de llic\u00e8ncia (que comen\u00e7a quan acaben els 60 dies de sol\u00b7licitud i dura 30 dies m\u00e9s, \u00e9s a dir, 90 dies en total).<\/p>\n\n\n\n<p class=\"wp-block-paragraph\"><strong>Resultat: les tasques A, C, D, E, F, G i H s\u00f3n cr\u00edtiques.<\/strong> La redacci\u00f3 del projecte executiu (B) t\u00e9 un marge de 45 dies i, per tant, no \u00e9s cr\u00edtica. Pots redistribuir hores d&#8217;equip en les primeres setmanes sense posar en risc el calendari.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Sense aquest an\u00e0lisi, \u00e9s f\u00e0cil caure en l&#8217;error de dedicar esfor\u00e7os a la feina visible (el projecte executiu) mentre la tramitaci\u00f3 administrativa, que \u00e9s la que marca el ritme real, avan\u00e7a sense el seguiment que li correspon.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\"><span class=\"ez-toc-section\" id=\"Quan_combinar_el_CPM_amb_el_diagrama_de_Gantt\"><\/span>Quan combinar el CPM amb el diagrama de Gantt<span class=\"ez-toc-section-end\"><\/span><\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">El CPM i el <strong>Gantt<\/strong> no s\u00f3n eines alternatives: es complementen. El Gantt mostra la <strong>planificaci\u00f3 en el temps de manera visual<\/strong>, tasca per tasca, amb dates d&#8217;inici i fi. El CPM afegeix la capa d&#8217;<strong>an\u00e0lisi de depend\u00e8ncies<\/strong> i identifica on no hi ha marge d&#8217;error.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">La combinaci\u00f3 \u00e9s especialment \u00fatil quan:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li>El projecte t\u00e9 <strong>m\u00faltiples agents externs<\/strong> (administracions, promotors, industrials) amb terminis que no controles.<\/li>\n\n\n\n<li><strong>Gestiones diversos enc\u00e0rrecs en paral\u00b7lel<\/strong> i has de repartir hores d&#8217;equip entre projectes.<\/li>\n\n\n\n<li><strong>Detectes desviacions<\/strong> i necessites saber r\u00e0pidament si afecten la data de lliurament o si tens marge per absorbir-les.<\/li>\n\n\n\n<li><strong>Est\u00e0s en fase de proposta<\/strong> i necessites un calendari cre\u00efble que el client pugui entendre i validar.<\/li>\n<\/ul>\n\n\n\n<blockquote class=\"wp-block-quote is-layout-flow wp-block-quote-is-layout-flow\">\n<p class=\"wp-block-paragraph\">Molts estudis utilitzen el Gantt com a document de comunicaci\u00f3 amb el client i el CPM com a eina interna de control.<\/p>\n<\/blockquote>\n\n\n\n<p class=\"wp-block-paragraph\">El m\u00e9s important \u00e9s que el cap de projecte tingui clar, en cada moment, quines tasques no poden esperar.<\/p>\n\n\n\n<div style=\"height:39px\" aria-hidden=\"true\" class=\"wp-block-spacer\"><\/div>\n\n\n\n<p class=\"has-text-align-center wp-block-paragraph\"><strong>Vols veure com planificar projectes amb Coneix?<\/strong><br>T\u2019ho mostren en una demo sense comprom\u00eds:<\/p>\n\n\n\n<div style=\"height:12px\" aria-hidden=\"true\" class=\"wp-block-spacer\"><\/div>\n\n\n\n<div class=\"wp-block-buttons is-content-justification-center is-layout-flex wp-container-core-buttons-is-layout-fe48e5de wp-block-buttons-is-layout-flex\">\n<div class=\"wp-block-button\"><a class=\"wp-block-button__link wp-element-button\" href=\"https:\/\/coneix.com\/ca\/contact\/\" target=\"_blank\" rel=\"noreferrer noopener\">Demana una demo de Coneix<\/a><\/div>\n<\/div>\n\n\n\n<div style=\"height:100px\" aria-hidden=\"true\" class=\"wp-block-spacer\"><\/div>\n","protected":false},"excerpt":{"rendered":"<p>Hi ha projectes que comencen b\u00e9, amb un calendari ben definit i un equip coordinat, i que, malgrat aix\u00f2, acaben amb retards que ning\u00fa sap ben b\u00e9 d&#8217;on han sortit. [&hellip;]<\/p>\n","protected":false},"author":7,"featured_media":9462,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"_et_pb_use_builder":"off","_et_pb_old_content":"","_et_gb_content_width":"","inline_featured_image":false,"footnotes":""},"categories":[146],"tags":[],"class_list":["post-9467","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-consejos"],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v28.0 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>El cam\u00ed cr\u00edtic (CPM) per a projectes d&#039;arquitectura i enginyeria | Coneix<\/title>\n<meta name=\"description\" content=\"El CPM identifica quines tasques d&#039;un projecte no admeten retard. Apr\u00e8n a aplicar-ho en projectes d&#039;arquitectura i enginyeria amb un exemple.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/coneix.com\/ca\/cpm-cami-critic\/\" \/>\n<meta property=\"og:locale\" content=\"ca_ES\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"El cam\u00ed cr\u00edtic (CPM) per a projectes d&#039;arquitectura i enginyeria | Coneix\" \/>\n<meta property=\"og:description\" content=\"El CPM identifica quines tasques d&#039;un projecte no admeten retard. Apr\u00e8n a aplicar-ho en projectes d&#039;arquitectura i enginyeria amb un exemple.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/coneix.com\/ca\/cpm-cami-critic\/\" \/>\n<meta property=\"og:site_name\" content=\"Coneix\" \/>\n<meta property=\"article:published_time\" content=\"2026-06-26T11:34:59+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2026-07-03T07:09:36+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/coneix.com\/wp-content\/uploads\/2026\/06\/CPM.png\" \/>\n\t<meta property=\"og:image:width\" content=\"650\" \/>\n\t<meta property=\"og:image:height\" content=\"450\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/png\" \/>\n<meta name=\"author\" content=\"Coneix\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:creator\" content=\"@Coneix\" \/>\n<meta name=\"twitter:site\" content=\"@Coneix\" \/>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"El cam\u00ed cr\u00edtic (CPM) per a projectes d'arquitectura i enginyeria | Coneix","description":"El CPM identifica quines tasques d'un projecte no admeten retard. Apr\u00e8n a aplicar-ho en projectes d'arquitectura i enginyeria amb un exemple.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/coneix.com\/ca\/cpm-cami-critic\/","og_locale":"ca_ES","og_type":"article","og_title":"El cam\u00ed cr\u00edtic (CPM) per a projectes d'arquitectura i enginyeria | Coneix","og_description":"El CPM identifica quines tasques d'un projecte no admeten retard. Apr\u00e8n a aplicar-ho en projectes d'arquitectura i enginyeria amb un exemple.","og_url":"https:\/\/coneix.com\/ca\/cpm-cami-critic\/","og_site_name":"Coneix","article_published_time":"2026-06-26T11:34:59+00:00","article_modified_time":"2026-07-03T07:09:36+00:00","og_image":[{"width":650,"height":450,"url":"https:\/\/coneix.com\/wp-content\/uploads\/2026\/06\/CPM.png","type":"image\/png"}],"author":"Coneix","twitter_card":"summary_large_image","twitter_creator":"@Coneix","twitter_site":"@Coneix","schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/coneix.com\/ca\/cpm-cami-critic\/#article","isPartOf":{"@id":"https:\/\/coneix.com\/ca\/cpm-cami-critic\/"},"author":{"name":"Coneix","@id":"https:\/\/coneix.com\/#\/schema\/person\/9428341db494719aaae24e1502fa8b96"},"headline":"CPM, la metodologia de planificaci\u00f3 de projectes del cam\u00ed cr\u00edtic","datePublished":"2026-06-26T11:34:59+00:00","dateModified":"2026-07-03T07:09:36+00:00","mainEntityOfPage":{"@id":"https:\/\/coneix.com\/ca\/cpm-cami-critic\/"},"wordCount":901,"commentCount":0,"publisher":{"@id":"https:\/\/coneix.com\/#organization"},"image":{"@id":"https:\/\/coneix.com\/ca\/cpm-cami-critic\/#primaryimage"},"thumbnailUrl":"https:\/\/coneix.com\/wp-content\/uploads\/2026\/06\/CPM.png","articleSection":["Consejos"],"inLanguage":"ca","potentialAction":[{"@type":"CommentAction","name":"Comment","target":["https:\/\/coneix.com\/ca\/cpm-cami-critic\/#respond"]}]},{"@type":"WebPage","@id":"https:\/\/coneix.com\/ca\/cpm-cami-critic\/","url":"https:\/\/coneix.com\/ca\/cpm-cami-critic\/","name":"El cam\u00ed cr\u00edtic (CPM) per a projectes d'arquitectura i enginyeria | Coneix","isPartOf":{"@id":"https:\/\/coneix.com\/#website"},"primaryImageOfPage":{"@id":"https:\/\/coneix.com\/ca\/cpm-cami-critic\/#primaryimage"},"image":{"@id":"https:\/\/coneix.com\/ca\/cpm-cami-critic\/#primaryimage"},"thumbnailUrl":"https:\/\/coneix.com\/wp-content\/uploads\/2026\/06\/CPM.png","datePublished":"2026-06-26T11:34:59+00:00","dateModified":"2026-07-03T07:09:36+00:00","description":"El CPM identifica quines tasques d'un projecte no admeten retard. Apr\u00e8n a aplicar-ho en projectes d'arquitectura i enginyeria amb un exemple.","breadcrumb":{"@id":"https:\/\/coneix.com\/ca\/cpm-cami-critic\/#breadcrumb"},"inLanguage":"ca","potentialAction":[{"@type":"ReadAction","target":["https:\/\/coneix.com\/ca\/cpm-cami-critic\/"]}]},{"@type":"ImageObject","inLanguage":"ca","@id":"https:\/\/coneix.com\/ca\/cpm-cami-critic\/#primaryimage","url":"https:\/\/coneix.com\/wp-content\/uploads\/2026\/06\/CPM.png","contentUrl":"https:\/\/coneix.com\/wp-content\/uploads\/2026\/06\/CPM.png","width":650,"height":450,"caption":"CPM"},{"@type":"BreadcrumbList","@id":"https:\/\/coneix.com\/ca\/cpm-cami-critic\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Inicio","item":"https:\/\/coneix.com\/ca\/homepage\/"},{"@type":"ListItem","position":2,"name":"CPM, la metodologia de planificaci\u00f3 de projectes del cam\u00ed cr\u00edtic"}]},{"@type":"WebSite","@id":"https:\/\/coneix.com\/#website","url":"https:\/\/coneix.com\/","name":"Coneix","description":"Software ERP de gesti\u00f3n especializado en arquitectura e ingenier\u00eda","publisher":{"@id":"https:\/\/coneix.com\/#organization"},"alternateName":"Coneix","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/coneix.com\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"ca"},{"@type":"Organization","@id":"https:\/\/coneix.com\/#organization","name":"Coneix Project Management SL","alternateName":"Coneix","url":"https:\/\/coneix.com\/","logo":{"@type":"ImageObject","inLanguage":"ca","@id":"https:\/\/coneix.com\/#\/schema\/logo\/image\/","url":"https:\/\/coneix.com\/wp-content\/uploads\/2024\/04\/CONEIX.-Logotipo.png","contentUrl":"https:\/\/coneix.com\/wp-content\/uploads\/2024\/04\/CONEIX.-Logotipo.png","width":191,"height":74,"caption":"Coneix Project Management SL"},"image":{"@id":"https:\/\/coneix.com\/#\/schema\/logo\/image\/"},"sameAs":["https:\/\/x.com\/Coneix","https:\/\/es.linkedin.com\/company\/coneix-project-management-sl","https:\/\/www.youtube.com\/user\/CONEIXPM"]},{"@type":"Person","@id":"https:\/\/coneix.com\/#\/schema\/person\/9428341db494719aaae24e1502fa8b96","name":"Coneix","image":{"@type":"ImageObject","inLanguage":"ca","@id":"https:\/\/secure.gravatar.com\/avatar\/4f48b365d55f0be85345169ba4caffa4ba66c5ec1a4e62fce13e6d3580d968f1?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/4f48b365d55f0be85345169ba4caffa4ba66c5ec1a4e62fce13e6d3580d968f1?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/4f48b365d55f0be85345169ba4caffa4ba66c5ec1a4e62fce13e6d3580d968f1?s=96&d=mm&r=g","caption":"Coneix"}}]}},"_links":{"self":[{"href":"https:\/\/coneix.com\/ca\/wp-json\/wp\/v2\/posts\/9467","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/coneix.com\/ca\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/coneix.com\/ca\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/coneix.com\/ca\/wp-json\/wp\/v2\/users\/7"}],"replies":[{"embeddable":true,"href":"https:\/\/coneix.com\/ca\/wp-json\/wp\/v2\/comments?post=9467"}],"version-history":[{"count":3,"href":"https:\/\/coneix.com\/ca\/wp-json\/wp\/v2\/posts\/9467\/revisions"}],"predecessor-version":[{"id":9483,"href":"https:\/\/coneix.com\/ca\/wp-json\/wp\/v2\/posts\/9467\/revisions\/9483"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/coneix.com\/ca\/wp-json\/wp\/v2\/media\/9462"}],"wp:attachment":[{"href":"https:\/\/coneix.com\/ca\/wp-json\/wp\/v2\/media?parent=9467"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/coneix.com\/ca\/wp-json\/wp\/v2\/categories?post=9467"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/coneix.com\/ca\/wp-json\/wp\/v2\/tags?post=9467"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}